Calculates the standard cost of manufactured products.
The Calculate Standard Costs process is run to generate the standard (= theoretical) cost.
Cost information is set up in several screens:
For raw material the price list information is used for the cost of the P-. The purchase price list that is used for the raw material cost is marked as default:

The cost information that is calculated for a product P+ is used when that product is a P- for another operation.
The formula that is used by the process is the following:
(Cost of Cost Center + Cost Employees + Cost Machines + Indirect Costs) + (Quantity P- x Cost P-) = the cost per unit.
When the costs of the cost center, machines, employees and indirect costs are calculated they are multiplied by different values depending of their unit of measure:
For Indirect costs the additional unit of measure percentage is available. This adds the defined percentage to the total cost calculated (cost center, employee, machine, indirect costs and P- products). For example if defined as 1.15, an additional 15% is added to the cost.
Note:
For the Indirect Cost to be included correctly, the following configuration is important in the Indirect Cost screen:
This way the standard cost for each operation is calculated.

The outcome of the calculation appears in the tabs of the Process Plan: In the Employee, Machine and Indirect Cost tabs, the result of the costs are automatically populated. Results can be reviewed on the Standard Cost Report.